Legal Duties and Site Management

On a project with more than one contractor, whose directions must each contractor comply with?

AWhichever contractor was on site first, as they know the job best
BOnly the client’s architect
CThe building control inspector’s
DThe principal designer’s or the principal contractor’s ✓

Answer & explanation

The correct answer is The principal designer’s or the principal contractor’s.

Regulation 15(3): where there is more than one contractor, each must comply with any directions given by the principal designer or principal contractor, and with the relevant parts of the construction phase plan.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, cooperation. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumCDM 2015cooperation