Legal Duties and Site Management

Under CDM 2015, what must a contractor give each worker under their control?

AA printed copy of the full construction phase plan
BAppropriate supervision, instructions and information ✓
CTheir own first aid kit and a fire extinguisher
DA written contract approved by the principal designer

Answer & explanation

The correct answer is Appropriate supervision, instructions and information.

Regulation 15(8) of CDM 2015 says a contractor must provide each worker under their control with appropriate supervision, instructions and information.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, supervision. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

easyCDM 2015supervision