Legal Duties and Site Management
Which of these must the information a contractor gives its workers include, under CDM 2015?
AA copy of the client’s budget for the project
BThe names of every other contractor’s workers
CA suitable site induction, unless the principal contractor has already given one ✓
DThe full design drawings for the whole building, so they can check the work against them
Answer & explanation
The correct answer is A suitable site induction, unless the principal contractor has already given one.
Regulation 15(9) lists what the information must include: a suitable site induction (where the principal contractor hasn’t provided one), what to do in an emergency, and information on the risks.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, induction. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumCDM 2015induction
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Under CDM 2015, what must a contractor give each worker under their control?A contractor wants to take someone on for a task. What does CDM 2015 say about that person?What must a contractor do with the construction work they and their workers carry out?Before a contractor starts work on a site, what must have happened about site access?