Under CDM 2015, who must make sure a suitable site induction is provided on a project with a principal contractor?

AThe client
BThe principal designer
CThe principal contractor ✓
DEach worker for themselves

Answer & explanation

The correct answer is The principal contractor.

Regulation 13(4)(a): the principal contractor must ensure that a suitable site induction is provided.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, induction. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

easyCDM 2015induction