Legal Duties and Site Management
When planning how long work stages will take, what must the principal contractor take into account?
AThe general principles of prevention ✓
BOnly the client’s preferred finish date
CThe cheapest way to do each stage
DWhat the last project took
Answer & explanation
The correct answer is The general principles of prevention.
Regulation 13(2): when deciding how work stages are planned and estimating the time needed, the principal contractor must take into account the general principles of prevention.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, planning. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
hardCDM 2015planning
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
What must the principal contractor organise between the contractors on site?How long must the principal contractor make sure welfare facilities are provided on site?Under CDM 2015, who must make sure a suitable site induction is provided on a project with a principal contractor?When must the principal contractor prepare the written construction phase plan?