How long must the principal contractor make sure welfare facilities are provided on site?
AFrom the start and throughout the construction phase ✓
BOnly once the building is watertight
COnly during the first month
DOnly while more than 20 people are on site
Answer & explanation
The correct answer is From the start and throughout the construction phase.
Regulation 13(4)(c) requires Schedule 2 welfare facilities throughout the construction phase. HSE says they must be provided from the start and maintained throughout.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, welfare. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyCDM 2015welfare
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
When planning how long work stages will take, what must the principal contractor take into account?When must the principal contractor prepare the written construction phase plan?What must the principal contractor organise between the contractors on site?Once work has started, what should happen to the construction phase plan?