Legal Duties and Site Management
When must the principal contractor prepare the written construction phase plan?
AWithin a month of the construction work starting on site
BBefore the construction phase begins ✓
COnly if HSE asks for it
DWhen the job is handed over
Answer & explanation
The correct answer is Before the construction phase begins.
HSE says the principal contractor must prepare a written construction phase plan before the construction phase begins.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, construction phase plan. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyCDM 2015construction phase plan
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
How long must the principal contractor make sure welfare facilities are provided on site?Once work has started, what should happen to the construction phase plan?When planning how long work stages will take, what must the principal contractor take into account?Under CDM 2015, when must the principal contractor consult workers about matters affecting their health, safety or welfare?