Once work has started, what should happen to the construction phase plan?

AIt should be filed away until the end of the job
BIt should only ever be changed by the client, never by the principal contractor
CIt should be put into practice, and regularly reviewed and revised ✓
DIt should be replaced by the risk assessments

Answer & explanation

The correct answer is It should be put into practice, and regularly reviewed and revised.

HSE says the principal contractor must implement the construction phase plan and regularly review and revise it.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, construction phase plan. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumCDM 2015construction phase plan