Legal Duties and Site Management
Once work has started, what should happen to the construction phase plan?
AIt should be filed away until the end of the job
BIt should only ever be changed by the client, never by the principal contractor
CIt should be put into practice, and regularly reviewed and revised ✓
DIt should be replaced by the risk assessments
Answer & explanation
The correct answer is It should be put into practice, and regularly reviewed and revised.
HSE says the principal contractor must implement the construction phase plan and regularly review and revise it.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, construction phase plan. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumCDM 2015construction phase plan
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
When must the principal contractor prepare the written construction phase plan?Under CDM 2015, when must the principal contractor consult workers about matters affecting their health, safety or welfare?How long must the principal contractor make sure welfare facilities are provided on site?Under regulation 14 of CDM 2015, what can workers or their representatives ask the principal contractor for?