Legal Duties and Site Management
What must the principal contractor organise between the contractors on site?
AA shared bank account
BCooperation, including between contractors who follow each other on site ✓
CA competition between the contractors to see who can finish their part of the job fastest
DOne shared set of tools
Answer & explanation
The correct answer is Cooperation, including between contractors who follow each other on site.
Regulation 13(3)(a): the principal contractor must organise cooperation between contractors, including successive contractors on the same construction site.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, cooperation. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumCDM 2015cooperation
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Under CDM 2015, who must make sure a suitable site induction is provided on a project with a principal contractor?When planning how long work stages will take, what must the principal contractor take into account?Who must plan, manage, monitor and coordinate health and safety for the whole construction phase?How long must the principal contractor make sure welfare facilities are provided on site?